Your supplier sends the first articles with a 40-page inspection report, and production is waiting on your signature. Every dimension is marked "pass" and the report looks complete — yet the question you are really being asked is not whether those three parts measured in tolerance. It is whether the next 10,000 will.
Approve production only when three things are true at once: every ballooned characteristic on the drawing has an actual measured value inside its tolerance, the material and process certificates match the purchase order, and the capability study shows Ppk of at least 1.67 on critical characteristics — 1.33 at the absolute minimum, with your written agreement. A report that only says "all dimensions OK" proves nothing about the next 10,000 parts.
This guide walks through a first article inspection report (FAIR) in the order you should read it: identity, dimensional results, certificates, then capability. It uses the AS9102 layout because that three-form structure is the clearest template in common use, and because most of the report formats you will meet outside aerospace borrow from it — but the reading method works on any supplier’s own form, as long as you insist on the same four pieces of evidence.
What a first article inspection actually proves — and what it does not
A first article inspection (FAI) is a documented check that the first production run — made on production tooling, with production materials, on the production process — can make a part that meets every requirement on the drawing and in the order. It is not a sample check and it is not a routine incoming inspection. Routine inspection samples parts during an ongoing run and monitors a process that is already approved. FAI is a one-time, comprehensive verification performed before the run is approved to proceed, and it validates the process, not just the part in front of you.
Three distinctions decide whether the report in your hands is worth anything. First, the parts must come from the first production run on production-intent tooling and programs. A part made on prototype tooling or an offline process does not qualify as a first article, however well it measures. Second, a full FAI accounts for every design characteristic on the drawing: each dimension, note and specification gets a number — a "balloon" — and every number gets a result. Third, approving a first article is not blanket acceptance of later production. The aerospace standard itself describes FAI as verification that the production process can consistently produce conforming characteristics, and states that it is not a product acceptance document. Your approval releases the process, not every future shipment.
The formal home of FAI is aerospace. SAE AS9102 defines the requirements and the report format, and the current text is AS9102C, issued 2023-06-28, with EN 9102:2024 as the European edition. Automotive customers run the equivalent exercise under PPAP, the Production Part Approval Process defined by AIAG, and German automotive buyers under VDA 2. For machinery, hydraulics, energy or laboratory equipment there is usually no governing standard at all — only the customer’s own sample report. That is why the purchase order matters more than the standard: if the order names AS9102C, work to that revision; if it names PPAP, deliver that package; if it names nothing, agree a first-sample report anyway, with a ballooned drawing, measured values for the characteristics that matter, and the material certificate. Ertas Engineering’s AS9102 guide sets out the three forms and the current editions in full, and it is the clearest public summary of the standard I have found.
FAI is the last gate, not the first: it comes after the mold design has been reviewed and approved — which is why you should review the DFM report before the mold is approved rather than discovering design problems at the first article stage. If your order is automotive, ask for PPAP instead: a first article report checks one part characteristic by characteristic, while PPAP proves the whole process, wrapping dimensional results, material and performance tests, process documents and a part submission warrant into one submission. A supplier who sends you one when you asked for the other has not answered your question.
Step 1 — the five-minute identity check
Start with Form 1, Part Number Accountability, or its equivalent on a supplier’s own form. This page answers one question: is this report about the part you ordered, at the revision you released? If anything here is wrong, stop — the measurements on the following pages belong to a different part or a different drawing, and reading further wastes your time.
Check the part number and revision, the drawing number and revision, the FAIR number, and whether the submission is a full or a partial FAI. A partial FAI points to a baseline part number and covers only the characteristics affected by a change; everything else is still covered by the earlier approved report. Check the nonconformance question — Form 1 asks directly whether any nonconformance exists — and check the signatures and dates. An unsigned report, or one signed before the measurements were taken, is a draft, not evidence.
| Identity mismatch | What it usually means | What to do |
|---|---|---|
| Drawing revision on the report is older than the released revision | Parts were made — or measured — against a superseded drawing | Return the report; ask for a new FAI against the current revision |
| Part number matches but the revision does not | A change was made after the FAI and never re-validated | Ask whether the change affects fit, form or function; if it does, a partial FAI is due |
| "Full FAI" is claimed but Form 3 has fewer rows than balloons on the drawing | Characteristics were skipped, or the ballooned drawing is incomplete | Count the balloons; the highest Form 3 number should equal the balloon count |
| Nonconformance is marked "No" but a Form 3 row is out of tolerance | The report contradicts itself | Treat the report as failed until the supplier explains the discrepancy in writing |
| No signature, or a signature dated before the inspection | The report was assembled, not reviewed | Ask for a signed copy; do not approve an unsigned report |
This check takes five minutes and it catches a surprising share of bad reports. A supplier who cannot keep part number and revision straight on page one is unlikely to have measured carefully on page twenty.
Step 2 — read the ballooned drawing against Form 3
Form 3, Characteristic Accountability, is where the measuring work sits, and it is the section that decides the approval. Take the ballooned drawing — the drawing with every inspectable feature circled and numbered — and read it against Form 3 line by line. Each balloon number becomes one Form 3 row, with the requirement from the drawing, the actual measured result, the gauge or tooling used, and any nonconformance reference. If a note on the drawing contains several requirements, each one needs its own number.
The first thing to check is completeness. Count the balloons on the drawing and compare with the highest Form 3 characteristic number. The two should be equal: 142 balloons and 137 Form 3 lines means five characteristics were skipped, and the package should be rejected on that alone. Then check the results column. Every row must carry an actual measured value, not "OK", not "pass", and not a repeat of the tolerance. A result column that echoes the requirement signals that nothing was measured. Where a feature is acceptable only through a bonus tolerance, the actual value is recorded together with that fact.
The second thing to check is the measurement method. The method must match the tolerance: a coordinate measuring machine (CMM) for positional and datum features, optical scanning for freeform surfaces, gauging for attribute acceptance. The report should identify the measuring equipment and trace it to calibration records. A tight tolerance measured with an uncalibrated hand caliper is not evidence; it is a guess written down neatly. This is the same logic that governs what tolerances injection molding can realistically hold — a tolerance is only as real as the measurement behind it — and it applies just as much to machined features, where the same question is what tolerances CNC machining can hold.
The table below shows what a clean Form 3 section looks like for a small molded housing cover. It is an illustrative example with invented numbers, included so you can see the shape of a good report — not a real inspection result.
| Balloon | Characteristic | Requirement | Measured result | Method | Verdict |
|---|---|---|---|---|---|
| 1 | Cover length | 120.00 ±0.15 mm | 120.04 mm | CMM | Pass |
| 2 | Bore diameter | 25.00 ±0.05 mm | 24.99 mm | Bore gauge | Pass |
| 3 | Boss height | 8.00 ±0.10 mm | 8.06 mm | Height gauge | Pass |
| 4 | Flatness, mating face | 0.10 mm max | 0.06 mm | CMM | Pass |
| 5 | Surface finish, outer face | SPI B-2 | B-2 | Visual + comparison plaque | Pass |
Note what makes this table usable: every row has a number, a requirement, an actual value and a method. If your supplier’s report has a "Result" column full of ticks, ask for the numbers. You cannot judge capability, trend or risk from a tick — and if a dimension drifts out of tolerance on the next run, you will have no baseline to compare against.
Also check the parts the report is based on. The standard works from a representative part of the first production run, and customer clauses commonly require a ballooned drawing with 100% of characteristics and a minimum of three pieces fully inspected. Three pieces prove the process made three conforming parts; they do not prove capability. That is what the capability study in Step 4 is for: the dimensional report answers "did these parts measure in tolerance", while the capability study answers "will the process keep doing so".
Step 3 — check the material and process certificates
Form 2, Product Accountability, records the raw materials, special processes and functional tests behind the part: specification, supplier, certificate numbers and test results. Every line must link to a verifiable document — a mill test report or a certificate of conformity — not to a statement that a certificate exists somewhere.
For a molded part, check that the resin grade and lot on the certificate match the grade and lot named in the purchase order, and that the certificate carries actual test results rather than a bare statement of conformity. A certificate of conformity says the material meets the specification; an inspection certificate with test results shows the numbers. For a machined part, check the metal heat or lot number the same way, and check any special process — anodizing, plating, heat treatment — for the performing supplier and its certificate number. Functional tests, where the drawing calls for them, need a procedure number and an acceptance report number, not a line that says "tested OK".
Two failures recur here. The first is a certificate for the wrong lot: the resin in the parts is from lot B, the certificate is for lot A, and nobody noticed because the grade name matches. The second is a missing special-process certificate, usually for a coating or a heat treatment done by a sub-supplier. If a process on the drawing has no certificate line on Form 2, the report is incomplete — send it back and ask for the missing document rather than approving around it.
Step 4 — judge capability: Cpk, Ppk, and the worked check
This is the step most buyers skip, and it is the step that decides whether approval is safe. Dimensional results tell you the measured parts were in tolerance. Capability indices tell you how much margin the process has, and therefore how likely the next parts are to stay in tolerance. A process can pass every measured dimension and still be incapable — and that is exactly the case the worked example below shows.
Two indices matter, and they are not interchangeable. Cpk uses the within-subgroup standard deviation: the variation inside small groups of consecutive parts, which describes what the process can do when it is running steadily. Ppk uses the overall standard deviation of every measurement in the study, which includes the drift between subgroups — material lot changes, shift changes, machine warm-up, cavity-to-cavity differences. Ppk is therefore the honest number for a first production run, because it measures how the process actually performed, including all the variation the customer will receive. Plastics Technology’s capability guide explains the two indices from the molder’s side, with the formulas and the reasoning behind the 1.33 threshold.
The formulas are the same for both indices; only the sigma changes:
- Cpk = the smaller of (USL − mean) / (3 × σ within-subgroup) and (mean − LSL) / (3 × σ within-subgroup)
- Ppk = the smaller of (USL − mean) / (3 × σ overall) and (mean − LSL) / (3 × σ overall)
The acceptance bands used across automotive PPAP submissions are: Ppk of 1.67 or higher is acceptable and supports full approval; 1.33 to 1.67 is conditional and needs written customer agreement with enhanced controls; below 1.33 is not acceptable. For ongoing series production the floor is Cpk of 1.33. A Cpk of 1.33 corresponds to roughly 63 defective parts per million when the process is centered; a Cpk of 1.00 corresponds to about 2,700 per million. Safety-critical characteristics are commonly held to 1.67.
Worked check: ten parts, all in tolerance, capability fails
Take a critical bore on a molded housing cover: 25.00 ±0.05 mm, so the upper limit is 25.05 mm and the lower limit is 24.95 mm. The supplier measures ten consecutive parts from the first run and reports these values in millimetres:
24.98, 25.01, 24.99, 25.00, 24.97, 25.02, 24.99, 25.00, 24.98, 25.01
Every one of the ten parts is inside the tolerance band, so the dimensional report passes. Now the capability check. The mean is 24.995 mm and the overall standard deviation is 0.0158 mm. Ppk is the smaller of (25.05 − 24.995) / (3 × 0.0158) = 1.16 and (24.995 − 24.95) / (3 × 0.0158) = 0.95. Ppk is 0.95 — below 1.33, so the process is not capable, even though not one measured part was out of tolerance. The mean sits 0.005 mm below nominal and the spread consumes most of the tolerance band; a small shift on the next run puts parts outside the limits.
This is a shortened illustration with ten readings so the arithmetic can be followed by hand; a real initial process study needs at least 100 readings in 25 or more subgroups, typically 300 consecutive parts or one full shift. But the lesson is the same at any sample size: passing dimensions and a capable process are two different claims, and only the capability number tests the second one.
What would fix this example? Center the process on nominal and tighten the spread. With a mean of 25.00 mm and an overall standard deviation of 0.012 mm, Ppk becomes 0.05 / (3 × 0.012) = 1.39 — above the 1.33 floor, though still below the 1.67 expected for an initial study, so the approval would be conditional rather than full. That is the conversation to have with the supplier: not "the parts are bad", but "the process needs centering, and here is the number that shows it".
One more signal is worth reading. Compare Cpk and Ppk from the same data: a large gap — Ppk much lower than Cpk — means the process moves between subgroups, through drift, tool wear or material lot changes. A ratio of Ppk to Cpk below about 0.8 is worth investigating. A supplier who reports only Cpk is showing you the process at its best and hiding the drift; always ask for Ppk on the same data.
The decision: approve, conditionally accept, or reject
Once the four steps are done, the decision writes itself. Use the table below as the decision rule, and put the decision in writing with the report reference, the drawing revision and the conditions attached.
| Evidence | Decision | What to write |
|---|---|---|
| Every ballooned characteristic has an actual measured value in tolerance; certificates match the order; Ppk ≥ 1.67 on critical characteristics | Approve | "FAI approved for [part number] Rev [X], FAIR [number], production released" |
| All dimensions in tolerance; Ppk 1.33–1.67 on one or more critical characteristics; no critical characteristic out of tolerance | Conditionally accept | Written agreement: containment inspection, the corrective action, and a re-study with a date — production released only under those conditions |
| Any critical characteristic out of tolerance, or Ppk < 1.33, or a characteristic with no measured value | Reject | Nonconformance raised; corrective action and a new first article required before production |
| Identity mismatch, missing certificate, balloon count short, unsigned report | Return the report | No decision made; the supplier corrects the package and resubmits |
A conditional acceptance is a real decision, not a polite rejection — but it must be written down with the condition attached, and the condition must have a date. "Approved, subject to the supplier improving capability" without a re-study date is an approval with no teeth, and the re-study will never happen. On a failure, the loop is standard: document the nonconformance with the actual measured value, find the root cause, correct it, make a new first article, and repeat the FAI — usually a partial FAI on the corrected characteristics only. A rejection is not a punishment: it is the quality system working as intended. The failure mode to avoid is discovering the same problem after the production run is already complete.
When a new or partial FAI is needed
Approval is not permanent. A full FAI is due for every new part number, and after that, any change that could affect conformance triggers a new FAI — full or partial, depending on the scope of the change. OpenBOM’s FAI guide lists the same triggers from the buyer’s side, and the table below follows the AS9102 events.
| Trigger event | Typical scope |
|---|---|
| New part number, first production run | Full FAI |
| Drawing or specification revision affecting fit, form or function | Partial — changed and added characteristics |
| Change in manufacturing source, process, inspection method, tooling or material | Partial — characteristics affected by the change |
| Change in the numerical control program or its translation | Partial — features produced by that program |
| Move of manufacturing to a new facility or location | Often full — the customer decides |
| Production lapse of two years or more | Full or partial, as the customer directs |
| Corrective action after a failed FAI | Partial — the nonconforming characteristics only |
The two-year lapse rule is worth remembering because it is the trigger most buyers forget. The clock runs from the completion of the last production run, not from the last FAI. If a part has not been made for two years, the process that made it — the tooling condition, the material lot, the operators, the machine settings — is no longer the process you approved, and a new first article is due before the next shipment. Agree the rule in the RFQ rather than discovering it when the parts are already on a truck.
What to put in the RFQ so the next FAI is usable
Most unreadable FAI reports are not caused by a bad supplier; they are caused by an order that never said what the report should contain. Settle these points in the RFQ, before the order is placed.
- Name the standard and revision — for example AS9102C — or state that a first-sample report to an agreed format is required.
- State full or partial FAI, and the baseline part number for a partial one.
- State how many pieces are to be fully inspected — three as a minimum is a common customer requirement — and whether a capability study is required, on which characteristics, and with how many readings.
- Name the capability thresholds in the order: Ppk of 1.67 on critical characteristics, 1.33 on significant characteristics, or whatever your product needs — and name the index, not just a number.
- Say who prepares the ballooned drawing and which CAD revision it is built from.
- Require actual measured values on every Form 3 row, with the measuring equipment identified and traceable to calibration.
- Require material and process certificates with the lot numbers, attached to the report — not available on request.
- State whether series shipments wait for approval of the first article, and who approves the report at your end.
- State what happens on failure: corrective action, a new first article, and a partial FAI on the corrected characteristics.
- State when a new FAI is due after a change — drawing revision, tooling, material, supplier, site, or a two-year production lapse.
Two of these points deserve emphasis. Naming the capability index matters because a supplier who is asked only for "Cpk 1.33" can deliver a within-subgroup number that hides drift; ask for Ppk on the initial study and Cpk for ongoing production, and the two numbers will tell you different and useful things. And settling the approval step matters because a report that arrives after the production run has shipped is a history document, not a gate.
Frequently asked questions
Is a first article inspection the same as PPAP?
No. A first article inspection checks one part, or a small number of parts from the first run, characteristic by characteristic, and is reported on the three AS9102 forms or an equivalent. PPAP is the automotive approval package from AIAG: it wraps dimensional results, material and performance tests, process documents and a part submission warrant into one submission, and it is judged on Ppk for the initial process study. If your customer is automotive, deliver PPAP; if you want to know whether a new process works before volume production, ask for the FAI report.
How many parts are measured in a first article inspection?
Typically one to three parts from the first production run, made on production tooling and the production process — some customer clauses require a minimum of three pieces fully inspected, with a ballooned drawing covering 100% of characteristics. The capability study is separate and needs far more data: at least 100 readings in 25 or more subgroups, typically 300 consecutive parts or one full shift.
Who prepares the ballooned drawing?
Whoever the purchase order says. The supplier usually prepares it from the released CAD data, and the buyer checks it — the check that matters is the count: the highest Form 3 number should equal the number of balloons, and every note on the drawing that contains several requirements needs a number of its own.
Can I approve a first article with a deviation?
Yes, but only in writing, only for a named characteristic, and only with the deviation recorded on the report and the corrective action agreed. A verbal "ship it, we will fix the drawing later" leaves you with parts that do not match any released revision. If the deviation changes fit, form or function, treat it as a design change and require a partial FAI on the corrected revision.
Before you sign
A first article inspection report is the last cheap moment in a project. Correcting a tool or a process before volume production costs a fraction of discovering the same problem in ten thousand shipped parts. Read the report in order — identity, dimensional results, certificates, capability — insist on actual measured values and on Ppk rather than Cpk alone, and put the decision in writing with the conditions attached. The supplier who sends you a clean, complete report has told you something valuable about how they work; the supplier who sends you a page of ticks has told you something too.
If you are sourcing custom injection molded or CNC machined parts and want the first article package agreed before the order is placed, send your drawing with the report format and capability thresholds your product needs. Tell us what to send in the request a quote form: a STEP file or 2D drawing, the material and quantities, the key tolerances and surface finish, the delivery region and your timing — and state which characteristics are critical, so the FAI is built around them from the start.